The optimization of auxiliary machinery in open-cast lignite mines: a case study of bulldozers
One of the most important prerequisites for the successful operation of the open-cast lignite mine is to carry out all the auxiliary works timely with the necessary quality. The most important and most commonly used auxiliary machines are bulldozers. Engaging time of bulldozers use is in direct relation with the coefficients of the time and capacity utilization of the continuous system for the excavation of coal and tailings, which indicates their importance. More than 100 bulldozers have been hired ...Dragan Ignjatović, Predrag Jovančić, Stevan Đenadić, Ivan Janković, Ivica Ristović. "The optimization of auxiliary machinery in open-cast lignite mines: a case study of bulldozers" in 7th International Symposium Mining and Environmental Protection, University of Belgrade, Faculty of Mining and Geology, Belgrade, Serbia (2019) М33
-
Multi-Criteria Fuzzy-Stochastic Diffusion Model of Groundwater Control System Selection
When considering data and parameters in hydrogeology, there are often questions of uncertainty, vagueness, and imprecision in terms of the quantity of spatial distribution. To overcome such problems, certain data may be subjectively expressed in the form of expert judgment, whereby a heuristic approach and the use of fuzzy logic are required. In this way, decision-making criteria relating to an optimal groundwater control system do not always have a numerical value. Groundwater control scenarios (alternatives) are identified through hydrodynamic ...expert judgment, linguistic variables, fuzzy dynamic TOPSIS, hydrogeology, groundwater control system, open-cast mine, geometric Brownian motionDušan Polomčić, Zoran Gligorić, Dragoljub Bajić, Miloš Gligorić, Milanka Negovanović. "Multi-Criteria Fuzzy-Stochastic Diffusion Model of Groundwater Control System Selection" in Symmetry, MDPI AG (2019). https://doi.org/10.3390/sym11050705 М22
-
Concept od predictive hydrodynamic calculations: An overview of the case studies from Serbia
Dušan Polomčić, Dragoljub Bajić, Jelena Ratković, Vesna Ristić Vakanjac, Marina Čokorilo Ilić (2019)groundwater management, hydrodynamic model, multiple-criteria decision making, open cast mine, groundwater source.0Dušan Polomčić, Dragoljub Bajić, Jelena Ratković, Vesna Ristić Vakanjac, Marina Čokorilo Ilić. "Concept od predictive hydrodynamic calculations: An overview of the case studies from Serbia" in National Conference with international participation “Geosciences 2019”, Bulgaria, 2019, Sofia : Bulgarian Geological Society (2019) М34
-
Analiza primene višekriterijumskih metoda u optimizaciji izbora hidruličnih bagera na površinskim kopovima uglja
Hidraulični bageri primenjuju se u različitim oblastima privrede a najzastupljeniji su u građevinarstvu i rudarstvu. Na površinskim kopovima sa kontinualnim sistemima, klasifikuju kao pomoćna mehanizacija a na površinskim kopovima sa diskontinualnim sistemima, kao osnovna mehanizacija. Kako je u oba slučaja njihova primena neizostavna, važno je izvršiti adekvatnu analizu postojećih podataka, u cilju optimizacije izbora tipa hidrauličnog bagera u odnosu na uslove rada datog površinskog kopa. U radu su opisane različite višekriterijumske metode koje su korišćene za analizu hidrauličnih bagera. ...Stevan Đenadić, Predrag Jovančić, Dragan Ignjatović, Filip Miletić, Ivan Janković. "Analiza primene višekriterijumskih metoda u optimizaciji izbora hidruličnih bagera na površinskim kopovima uglja" in Tehnika, Centre for Evaluation in Education and Science (CEON/CEES) (2019). https://doi.org/10.5937/tehnika1903369D М52
-
Noise management - Case study Buvač open cast mine
Aleksandar Cvjetić, Ljubica Figun, Vladimir Milisavljević, Uroš Pantelić, Aleksandra Tomašević (2015)Aleksandar Cvjetić, Ljubica Figun, Vladimir Milisavljević, Uroš Pantelić, Aleksandra Tomašević. "Noise management - Case study Buvač open cast mine" in Mining and Environmental Protection, 5th International Symposium, Beograd:Rudarsko-geološki fakultet, Center for Environmental Engineering (2015): 410-419 M33
-
Hydrodynamic model of the open-cast mine Tamnava - West field
Polomčić Dušan, Bajić Dragoljub, Ratković Jelena, Šubaranović Tomislav, Ristić Vakanjac Vesna (2017)Polomčić Dušan, Bajić Dragoljub, Ratković Jelena, Šubaranović Tomislav, Ristić Vakanjac Vesna. "Hydrodynamic model of the open-cast mine Tamnava - West field" in Proceedings of the VIII International Conference “Coal 2017”, Belgrade:Yugoslav Opencast Mining Committee (2017): 327-339 M33
-
Reliability of Rubber Conveyor Belts as a Part of the Overburden Removal System - Case Study: Tamnava-east Field Open Cast Mine
Bugarić Uglješa, Tanasijević Miloš, Polovina Dragan, Ignjatović Dragan, Jovančić Predrag. "Reliability of Rubber Conveyor Belts as a Part of the Overburden Removal System - Case Study: Tamnava-east Field Open Cast Mine" in Journal of TEHNIČKI VJESNIK = TECHNICAL GAZETTE 21 no. 5 (2014): 925-932 M23
-
A hydrogeological model of the open-cast mine Tamnava - West Field (Kolubara Coal Basin, Serbia)
Jelena Ratković, Dušan Polomčić, Dragoljub Bajić, Bojan Hajdin. "A hydrogeological model of the open-cast mine Tamnava - West Field (Kolubara Coal Basin, Serbia)" in Underground Mining Engineering no. 29, Belgrade : University of Belgrade - Faculty of mining and geology (2016): 43-54 M52
-
Application of the Fuzzy theory in the evaluation of operating parameters of auxiliary mechanization on open-cast coal mine, case study: pipelayers
Achieved operating parameters are the main indicator of the work quality and selection of mining machines. The effectiveness of a coal mine is correlated with the availability of basic and auxiliary machines. The main task of auxiliary machines in lignite mines is to achieve optimal working conditions. From an economic point of view, auxiliary machines generate up to 20% of the lignite mines' total costs. These are the primary reasons for analyzing their current work and making decisions in ...Stevan Djenadić, Miloš Tanasijević, Filip Miletić, Predrag Jovančić. "Application of the Fuzzy theory in the evaluation of operating parameters of auxiliary mechanization on open-cast coal mine, case study: pipelayers" in 8th Balkan Mining Congress, Belgrade, September 28-30, Rudarski instutut (2022) М33
-
Primena modela transporta idealne čestice na primeru razvoja Površinskog kopa Jakovačka Kumša
Hidrodinamičkim proračunima transporta „idealne“ čestice prikazan je uticaj eksploatacije peskova sa površinskog kopa „Jakovačka Kumša“ na beogradsko izvorište podzemnih voda. Potencijalnu opasnost od zagađenja podzemnih voda izvorišta za vodosnabdevanje čini skup različitih procesa koji se odvijaju na površinskom kopu. U radu je prikazano poređenje dva modela transporta idealne čestice. Prvi model se odnosi na analizu putanje i vremena putovanja idealne čestice od površinskog kopa do izvorišta za stanje pre otvaranja kopa, dok se drugi model odnosi na stanje kada ...upravljnje podzemnim vodama, zaštita podzemnih voda, hidrodinamički model, metoda praćenja „idealne“ čestice, modflow, modpathDušan Polomčić, Dragoljub Bajić, Vesna Ristić Vakanjac, Marina Čokorilo Ilić. "Primena modela transporta idealne čestice na primeru razvoja Površinskog kopa Jakovačka Kumša" in 9. Međunarodni simpozijum o upravljanju prirodnim resursima, Faculty of Management, Zajecar, Megatrend University, Belgrade (2019) М33
-
Multi-Criteria Approach for Selecting Optimal Dozer Type in Open-Cast Coal Mining
Ivan Janković, Stevan Đenadić , Dragan Ignjatović , Predrag Jovančić , Tomislav Šubaranović, Ivica Ristović (2019)Ivan Janković, Stevan Đenadić , Dragan Ignjatović , Predrag Jovančić , Tomislav Šubaranović, Ivica Ristović . "Multi-Criteria Approach for Selecting Optimal Dozer Type in Open-Cast Coal Mining" in Energies, MDPI (2019). https://doi.org/https://doi.org/10.3390/en12122245 М22
-
Simulation of groundwater regime and quantification of groundwater balance by means of hydrodynamic analysis: Case of open-cast mine 'Jakovačka Kumša'
Hidrodinamička analiza, kao metodološki postupak, korišćena je za simulaciju režima i kvantifikaciju bilansa podzemnih voda na širem području Površinskog kopa „Jakovačka Kumša“. Istražni prostor obuhvata i deo beogradskog izvorišta podzemnih voda koje se nalazi u neposrednoj blizini površinskog kopa, u priobalju reke Save. Na površinskom kopu se vrši eksploatacija peska, koji se koristi kao građevinski materijal. Analizom i sintezom podataka koji se odnose na geološke i hidrogeološke ka-rakteristike područja, u radu je prikazan trodimenzionalni hidrogeološki model istražnog područja. Prevođenje ...hidrogeološki model, hidrodinamički model, izvorište podzemnih voda, numerička metoda konačnih razlika, ModflowDušan Polomčić, Dragoljub Bajić, Jelena Ratković, Đorđije Božović, Predrag Pajić. "Simulation of groundwater regime and quantification of groundwater balance by means of hydrodynamic analysis: Case of open-cast mine 'Jakovačka Kumša'" in Tehnika, Centre for Evaluation in Education and Science (CEON/CEES) (2019). https://doi.org/10.5937/tehnika1901056P М52
-
History of the development of the hydrodynamic model of the open pit mine “Drmno”, Serbia
With the creation of a hydrodynamic model, the need for it usually ceases until some next moment when the model needs to be updated and used for the set task for the necessary project documentation or dedicated studies. It is relatively rare that almost every year the model is improved and used for forecast calculations. The paper presents the basic characteristics and development of the hydrodynamic model of the open pit mine “Drmno” for 25 years. This open pit ...Dušan Polomčić, Jelena Ratković, Vesan Ristić Vakanjac. "History of the development of the hydrodynamic model of the open pit mine “Drmno”, Serbia" in National Conference with International Participation “GEOSCIENCES 2023”, Review of the Bulgarian Geological Society , Sofia : Bulgarian Geological Society (2023) М33
-
History of the development of the hydrodynamic model of the open pit mine “Drmno”, Serbia
With the creation of a hydrodynamic model, the need for it usually ceases until some next moment when the model needs to be updated and used for the set task for the necessary project documentation or dedicated studies. It is relatively rare that almost every year the model is improved and used for forecast calculations. The paper presents the basic characteristics and development of the hydrodynamic model of the open pit mine “Drmno” for 25 years. This open pit ...Dušan Polomčić, Jelena Ratković, Vesna Ristić Vakanjac. "History of the development of the hydrodynamic model of the open pit mine “Drmno”, Serbia" in Review of the Bulgarian Geological Society, Bulgarian Geological Society (2023). https://doi.org/10.52215/rev.bgs.2023.84.3.307 М23
-
Dewatering system selection at the open cast Drmno using hydrodynamical forcasting calculations
Polomčić Dušan, Pavlović Vladimir, Šubaranović Tomislav. "Dewatering system selection at the open cast Drmno using hydrodynamical forcasting calculations" in X International Scientific Opencast Mining Conference OMC, Zlatibor: (2012): 275-290 M33
-
An overview of the application of modern methods of hydrodynamic calculations for groundwater control systems of open cast mines in Serbia
Polomčić Dušan, Bajić Dragoljub, Ratković Jelena, Ristić Vakanjac Vesna, Čokorilo Ilić Marina (2017)Polomčić Dušan, Bajić Dragoljub, Ratković Jelena, Ristić Vakanjac Vesna, Čokorilo Ilić Marina. "An overview of the application of modern methods of hydrodynamic calculations for groundwater control systems of open cast mines in Serbia" in Proceedings of the national conference with international participation „Geosciences 2017“, Sofia:Bulgarian Geological Society (2017): 143-144 M34
-
Effectiveness Analysis of Different Bucket-wheel Excavators
Coal production in open-pit lignite mines in the Republic of Serbia is performed with continuous work systems. In addition to coal production, the same systems are used for the exploitation of large quantities of overburden. According to the reliability concept, continuous systems are in linear connection. If the failure occurs in one part of the system, that will produce a downtime of the entire system. The initial and most important factor of continuous systems is the bucket-wheel excavator. It ...Stevan Đenadić, Predrag Jovančić, Dragan Ignjatović, Miloš Tanasijević, Filip Miletić. "Effectiveness Analysis of Different Bucket-wheel Excavators" in 8th International Conference Mining and Environmental Protection, Sokobanja, 22-25 September 2021, University of Belgrade, Faculty of Mining and Geology, Belgrade, Serbia (2021) М33
-
Analiza geomehaničke stabilnosti kosina na odlagalištima i površinskom kopu Ćeramide
Kako bi se nastavila eksploatacija dacita na površinskom kopu Ćeramide kod Rudnika, potrebno je izraditi novu projektnu dokumentaciju na osnovu novih overenih rezervi. Da bi se eksploatacija jalovine i dacita odvijala sigurno bez klizanja i obrušavanja stenskog materijala, neophodno je izvršiti proveru stabilnosti projektovanih kosina i na odlagalištima i na samom površinskom kopu. U ovom radu je upravo data analiza geomehaničke stabilnosti kosina na odlagalištima i površinskom kopu dacite Ćeramide kod Rudnika.Tomislav Šubaranović, Vladimir Čebašek, Bojan Dimitrijević, Veljko Rupar. "Analiza geomehaničke stabilnosti kosina na odlagalištima i površinskom kopu Ćeramide" in XV Međunarodna konferencija OMC 2022, Zlatibor, 12-15. oktobar 2022., Jugoslovenski komitet za površinsku eksploataciju (2022) М33
-
Failure Estimation of the Majdanpek Open Pit East Face Based on Inverse Velocity Model
The Majdanpek open pit mine south district is currently active mining prospect of copper ore exploitation in eastern Serbia. Its depth is approaching the termination depth and occurrences of large-scale instabilities and global instability of the final pit slope is possible. These can generate catastrophic mass movement inside an area that encloses a regional road route and the Pek River bed which is channelled along the outer contour of the pit. The displacements that were noted in early 2023, in the ...Miloš Marjanović, Stefan Milanović, Nikola Simić, Lazar Kričak. "Failure Estimation of the Majdanpek Open Pit East Face Based on Inverse Velocity Model" in Regional Symposium on Landslides in the Adriatic-Balkan Region, Belgrade, 15-18th May 2024, University of Belgrade, Faculty of Mining and Geology (2024). https://doi.org/10.18485/resylab.2024.6.ch46 М33
-
Стабилизација косине приступног пута површинског копа ћерамиде
У југоисточном делу површинског копа Ћерамиде дошло је до формирања клизног тела у косини насипа приступног пута. Клизно тело се привремено стабилизовало и исто се врло брзо може променити услед повећаних количина падавина и инфилтрације веће количине воде у тело косине чиме би се драстично изменила физичко-механичка својства стенског материјала у телу насипа пута и стенског масива у залеђини косине. Геомеханички услови санације клизишта у телу косине приступног пута су анализирани на основу могућности измене геометрије косине формирањем насипа ...Владимир Чебашек, Вељко Рупар, Јелена Мајсторовић Нецковић, Драгана Нишић, Урош Пантелић. "Стабилизација косине приступног пута површинског копа ћерамиде" in XVI међународна конференција ОМЦ 2024, Златибор, 9-12. октобар 2024. , Југословенски комитет за површинску експлоатацију (2024) М33